Permits have been issued by the City of Lincoln, and the Lincoln Clay Arts Center (LCAC) has selected trade contractors for the approved building renovations. LCAC is currently preparing for construction, with work scheduled to begin the first week of December.
Initial work will focus on reconstructing the side entrance stairs and laying the foundation for the ADA lift, followed by electrical and plumbing upgrades, and concluding with new main-level flooring and fresh paint throughout.
The kilns and the ADA lift have already been ordered, and LCAC is finalizing the remaining equipment needs for delivery in late January or early February. Although the project is running approximately six weeks behind schedule, the Center remains on track for a first-quarter opening in 2027.
On October 13, 2028, the City Council approved a 20-year ground lease with LCAC. The City Attorney is preparing the final lease for signature.
This past June, the City of Lincoln repaired the exterior windows and refreshed the building’s exterior—painting the window trim, doors, eaves, gutters, and downspouts. The City also cleared out stored furnishings and supplies to make way for work to begin by LCAC's trade contractors.
Be sure to follow our progress on our Facebook Page!
Construction Timeline
September – October 2026: Permits issued and trade contractors selected.
November 2026 - January 2027: Construction initiated and completed; equipment installed.
February 2027: Art Center prepares for its Grand Opening.
March 2027: Grand Opening.
Key Improvements Include:
Installing an ADA wheelchair lift for full accessibility
Upgrading plumbing, electrical, lighting elements and restroom facilities
Laying new flooring on the main level
Applying fresh paint throughout the interior
Final Steps
Once renovations are complete, LCAC will fit the space with essential studio equipment, including kilns, wedging tables, slab rollers, pottery wheels, and extruders.